Drywall has started and siding being finished up….

Online Journal of "Palmer" model in Autumn Vista Acres No Comments

Status of job as of April 2…framing done, siding almost there, rough in plumbing, electrical, hvac, and insulation all done, and drywall has started. Going into finish next week. Thanks to all the super-subs making it happen!

april-08-blog.jpg

Framing has started

Online Journal of "Palmer" model in Autumn Vista Acres No Comments

February 27, 08: Framing is moving along; trusses come next week. So roof will be on by the first week in March.